Hi,
I would like to know If and how a project activity can be reverted back to the "active" state, after the activity was marked "complete".
Sometimes a user will click the "complete" button by mistake instead of the "save" button, and there seems to be no way to correct that, even if I manually change the percent complete to 0%, the lifecycle state will still be "Complete", and the activity will not show up on the assignee's InBasket.
Any help will be greatly appreciated
Thanks,
Jo