Project Plan Start Date & Finish Date

rated by 0 users
This post has 2 Replies | 1 Follower

Top 75 Contributor
Posts 22
Points 390
Radhakrishnan Posted: Tue, Feb 2 2010 10:46 PM

Hi,

I have created one PROJECT like below structure.

Testing Product

·         Phase1 (WBS) : Designing

 

      Requirement Gathering (Activity)-1

             Leader                   : RK

             Plan Start Date    :  02/03/2010

             Plan Finish Date  :  02/24/2010

             Duration               :  16   

     Requirement Analyzing (Activity)-2

             Predecessor         : 1

             Leader                   : CHO

             Plan Start Date    :  02/25/2010

             Plan Finish Date  :  02/25/2010

             Duration               :  1

     Conclusion (Milestone)-1   

 

·         Phase2             : Drafting

---

---

Question:

If the Activity1 [Requirement Gathering] completed on the starting date itself {02/03/2010 itself}, Will Activity2 [Requirement Analyzing] automatically assign the work to Leader CHO In Basket or the Activity2 will wait for plan start date of {02/25/2010}.

Thanks & Regards,

RK

  • | Post Points: 20
Top 500 Contributor
Posts 3
Points 15

My testing shows that Activity2 will wait for plan start date before it's status becomes active, it will stay as pending until the plan start date arrives. It will not let you complete pendiog activities. Is there a way to change this behavoir. If Task1 is a predecessor to Task2 and Task 1 is completed early, then Task2 should show up in the Inbasket immediately. It is difficult to demo APQP functionality when the activities do not show up until then planned start data arrives. 

  • | Post Points: 5
Top 500 Contributor
Posts 3
Points 15

correction..., you can complete activities in the Pending state.

  • | Post Points: 5