Boeffen - Monday, July 12, 2010 9:50 AM:
Hi,
I am investigating if we want to migrate to ARAS, and have 1 question. Can ARAS handle BOMs with alternative parts? Either by having a single partnumber, with more suppliers, or by having a BOM where 1 position can have more partnumbers?
PS: is there a test-server/sandbox somewhere? Or a hosting solution with preinstalled ARAS standard setup?
Kind regards,
Mikkel
Yoann Maingon - Sunday, July 18, 2010 4:17 PM:
Hi,
Yes, in Aras Innovator both features are included in the initial installation. You can manage alternative parts related directly to a Part definition or it can be linked to its BOM instance (substitutes) which makes the change only possible in the context of this BOM.
you can contact me, Yoann Maingon, from Prodeos for some test on a hosted solution : [email protected]
Best Regards,
Yoann