<?xml-stylesheet type="text/xsl" href="https://www.aras.com/community/cfs-file/__key/system/syndication/rss.xsl" media="screen"?><rss version="2.0" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:slash="http://purl.org/rss/1.0/modules/slash/" xmlns:wfw="http://wellformedweb.org/CommentAPI/"><channel><title>Project Plan updation Query</title><link>https://www.aras.com/community/f/applications/3519/project-plan-updation-query</link><description>hi,

i created one project plan having two activity A and B, In which Activity A is Predecessor of Activity B

activity&amp;#160; &amp;#160; &amp;#160; predecessor&amp;#160; &amp;#160; &amp;#160; &amp;#160;plan start&amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160;plan finish&amp;#160; &amp;#160; &amp;#160; &amp;#160;duration

A&amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; &amp;#160; 12/28/2017&amp;#160; &amp;#160; &amp;#160; &amp;#160;</description><dc:language>ja-JP</dc:language><generator>Telligent Community 12</generator><item><title>RE: Project Plan updation Query</title><link>https://www.aras.com/community/thread/1168?ContentTypeID=1</link><pubDate>Fri, 05 Jan 2018 00:08:49 GMT</pubDate><guid isPermaLink="false">916d3f7e-8ddc-42f8-8d45-380822f51406:9d33136c-570c-4204-bd44-c90f952fb321</guid><dc:creator>R</dc:creator><description>hi Christopher Gillis

thanks for your reply , If I get any question while implementation, I will ask in the forum.&lt;div style="clear:both;"&gt;&lt;/div&gt;</description></item><item><title>RE: Project Plan updation Query</title><link>https://www.aras.com/community/thread/1167?ContentTypeID=1</link><pubDate>Thu, 04 Jan 2018 15:45:52 GMT</pubDate><guid isPermaLink="false">916d3f7e-8ddc-42f8-8d45-380822f51406:4a08720b-29d6-47eb-8fbd-a4b27c755be1</guid><dc:creator>Christopher Gillis</dc:creator><description>Hello,

There are a couple ways to accomplish this depending on how you expect the logic of the scheduling to work.

The first would be to make no change at all. The dates in the project plan are intended to be expected start and end dates with the actual dates being specified in the project completion dialog. If a predecessor activity is overdue, the next activity is also overdue and should be marked as such.

Alternatively, if you want the project plan to be dynamic, you could write an onAfterUpdate server event to increase the duration of the activity by the number of extra days it took to complete the activity. After making that change, the project plan should automatically reschedule based on the new duration which will push the start date of Activity B that many days forward.

We don&amp;#39;t currently have any examples of how to accomplish this, but if you have any specific questions while you work on the implementation, you can ask them here.

Chris

__________________________________

Christopher Gillis

Aras Labs Software Engineer&lt;div style="clear:both;"&gt;&lt;/div&gt;</description></item></channel></rss>