tbwork - Tuesday, November 8, 2011 10:17 AM:

 

When creating a process planner module, I only have one line available, i.e. only one operation.

How can I add additional line items/operations? In the help manual, an example with multiple line items is shown.

 

Thank you.



tbwork - Tuesday, November 8, 2011 1:09 PM:

Found it .... use the "insert" key on the keyboard.

 