vasant - Tuesday, June 12, 2012 2:48 AM:
Hi Experts,
In Aras OOTB Project Management How Can we Schedule Working Days?
There are Some Companies which is having Holiday on "Monday" or any other has "Friday".
If a Company is Working for alternate days then How can we Schedule the Project?
Then how it could be manageable?
Is it Possible?
Thanks & Regards,
Vasant
Note: In Aras Calendar we have option for "Weekend Days Off" but it is not feasible with all Conditions.
Boro - Tuesday, July 3, 2012 4:10 AM:
Hi
You can configure your original holiday using Exceptions tab on Calendars Item.
If you add new relationship rows in Exceptions tab and check the Day Off check-box column. Then Aras Scheduler treat the date as holiday.
Thanks.
Abhishek Srivastava - Tuesday, July 10, 2012 4:28 AM:
Hi,
You just go to the Administration section , select calendar option and create new business calender. just list out which day is leave in a calendar and save unlock close .
I hope this will be working.
with Regard
Abhishek Srivastava