DEVELOPERS FORUM - Attaching Process Planners to a Project

biztram - Friday, June 21, 2013 1:17 PM:

Hello,

there should be a way to attach a Process Planner to a Project - Activity.
You can watch it in the following video: https://www.youtube.com/watch?v=JaWiZhgR4_s at 1:38 minutes.

Everytime i click on Add Existing Deliverable aras is just asking about attaching a document, but not about a Project Planner.

I am grateful for any kind of help!

Thanks!

bitzram



Boro - Sunday, June 23, 2013 11:14 PM:

Hello bitzram,

The list of deliverable is controlled by "Deliverable" ItemType which defined as Poly Item.

You can add attaching items with configuring "Deliverable".

1.Open Deliverable Itemtype from TOC(Administration->ItemType) and switch "Poly Sources" tab.

2.Add itemtypes which you'd like to show on Add Deliverable dialog. (you can select "Process Planner") 

Thanks



biztram - Thursday, June 27, 2013 6:53 AM:

Thank you Boro,

this is exactly what i needed!