This discussion has been locked.
You can no longer post new replies to this discussion. If you have a question you can start a new discussion

SOLUTION - PROGRAM MANAGEMENT - Capturing and Analysing Project Costs

Brian - Sunday, May 3, 2009 8:48 PM:

Hi All,

In relation to Innovator 9.01 and the accompanying help file.

I have read through all of the information in the help regarding Projects and cannot see any way of recording planned/actual costs for the resource time planned/expended on individual activities or the project as a whole.

I noted that there is currently no labour rate associated with Users and that the help specifically says that the Time Recording information is not used anywhere but could be later.

Are there plans underway to expand the capabilities of the Project Management solution to address this shortfall in functionality?

Regards,

Brian.