SOLUTION - PROGRAM MANAGEMENT - Start Dates Not Updated Correctely

wings - Wednesday, June 24, 2009 4:01 PM:

I have task#1 start, say today, finish a week later; I have setup task#2 to start after #1 completes. When I first set it up, everything updated correctly. However if I change the completion date of #1 to an earlier date, #2 start date does not change.

 

Is this a bug? Or I should use it differently?