Boro - Monday, September 14, 2009 8:34 PM:
Hi All,
I don't understand the function of "Predecessor". When the plan day of activity passes the activity becomes active even if the predecessor is set. Is the function of predecessor such a specification??
Is there a way to keep "predecessor" rules?
I know same question has already posted on this forum. Should I modify the method?
http://www.aras.comhttp://www.aras.com/Community/forums/p/335/914.aspx#914
thanks
Andy - Wednesday, September 16, 2009 6:41 PM:
I think predecessors are only used for scheduling, and not activation.
Andy.
Boro - Wednesday, September 16, 2009 10:24 PM:
Hi Andy.
Thank you for your reply. I also thought similarly after I posted this question.
It is happy if predecessor rules apply for activation. I'm trying to think other ways.
Thanks