Hi,
I have a property called 'duration' in mpp_ProcessPlan and i would like to fill that Property value with sum of cycle time + setup time of all the operations associated with a process plan. how to write server side method for relationship Types…
Hi,
I would like to know how to set users not to modify nor delete when a item in process Plan is in released state. I'm working on Aras V12.0.
Thanks.
Hi,
I recently installed Aras Innovator V12.0. I was using Aras Innovator V11.Sp12 where all my work was done. Now, i would like to switch to V12.0, I have few tables around 9 tables in which two tables of Manufacturing Process Plan and Operations,…
Hi Folks,
I'm working on Manufacturing process plan in Aras innovator version 11 SP12. I would like to add other items, which have a relationship with operations, in the workbench to select, drag and drop the items into the operation. I tried to modify…
Hello,
I have a use case where I wanted to be able to use the MPP module to create process plans for more than one itemtype, ex. some process plans are based on parts and some are based on another itemtype. Is this possible? I know that you can use…
At the moment, we can add cycle times and setup times to operations, and cycle times to steps. But this information does not display anywhere once entered. That is fine, but at least if there was the ability to roll-up the cycle times of all the operations…
Hi folks, I have a question and i think you guys can help me. my question is how to change the property of operation number in process plan from Integer to a String. when i tried to change in the properties of mpp_operation which is a item type, it showing…